2002 Scoulton Mere

Driven by the Environment Agency's Asset Management Plan ( AMP3) Anglian Water Services set in motion a series of projects with Ewan Group plc, who in turn contracted the supply and installation of 3 borehole and 1 surface water logging systems to Halcyon Solutions.  

The driver for this scheme being the Habitats Directive which defined that reduced levels in the Mere in recent years was leading to concerns about stress to plant communities

 

Incremental Shaft Encoder mounted on 300mm Twinwall with sump and inlet pipe to the Mere

3 Observation Boreholes at end of Mere

Internal view of GRP Kiosk with 3 VF1e Data Loggers, 25mm ducts to each borehole

 